In short
For a non-resident, a Spanish mortgage usually takes six to ten weeks from a complete file to signing at the notary, plus the time needed beforehand for the NIE and documents. The final stretch is fixed by Law 5/2019: the binding offer (FEIN) must reach you at least ten calendar days before signing.
How long does it take to get a mortgage in Spain?
For a non-resident, our experience is six to ten weeks from a complete file to signing at the notary. The clock starts only when the lender has everything it needs: identification, income evidence, tax returns, bank statements and the origin of the funds. Before that, allow time to obtain an NIE, open a Spanish account and prepare translated documents.
The end of the process has a legal minimum that nobody can shorten. Under Law 5/2019, the lender must deliver the binding offer and the other pre-contract documents at least ten calendar days before signing, and you must see the notary before the signing day. Everything else depends on preparation.
The timeline at a glance
| Week | Step | Who | What can delay it |
|---|---|---|---|
| Before you reserve | Feasibility review, NIE, Spanish account, budget with taxes | You and your broker | NIE appointments, documents still abroad |
| Week 0 | Reservation, arras contract, file complete | You, the seller, both lawyers | A completion date that ignores the mortgage timetable |
| Weeks 1–3 | Lenders analyse the application | Lenders, your broker | Missing translations, unexplained funds |
| Weeks 2–4 | Valuation | Approved valuation company | Access to the property, a valuation below the price |
| Weeks 3–6 | Credit approval | The lender’s risk team | Questions on foreign income, debts or currency |
| Weeks 4–8 | FEIN, FiAE and draft contract; the ten days start | Lender | Changing the amount or terms after the offer |
| Weeks 5–10 | Transparency meeting at the notary | You or your representative, notary | A power of attorney that is not ready |
| Weeks 6–10 | Purchase and mortgage deeds signed | You, the seller, lender, notary | Funds not yet in Spain |
| After signing | Taxes paid, deeds registered | Agency or lawyer, Land Registry | Defects the registrar asks you to correct |
Week 0 is when your file is complete, often the week the arras contract is signed.
Before you reserve: what should you do first?
The most useful weeks are the ones before you choose a property:
- A feasibility review. Spanish lenders typically finance 60–70% of the lower of price and valuation for a non-resident, against 80% for a resident. As a working reference, the new instalment plus what you already pay at home should stay within about 30–35% of net income.
- The NIE, the foreigner identification number the notary needs for the deeds. Through a consulate it can take weeks; our NIE and bank account guide sets out the routes.
- A Spanish bank account, which most lenders require for the mortgage payments.
- A budget with taxes. Plan on a 30–40% contribution plus purchase taxes and costs, paid from your own funds. The purchase costs calculator gives the taxes by region, and the Spanish mortgage calculator the instalment.
If you are still deciding where to buy, the areas guide compares prices and taxes along the coast.
Reservation and the arras contract
A reservation takes the property off the market. The arras contract then fixes the price, the completion date and a deposit, commonly around 10% of the price. With penitential arras, article 1454 of the Civil Code lets the buyer withdraw by losing the deposit and the seller by returning it doubled. Catalonia has its own rules; our guide to arras and mortgages in Catalonia explains them.
The mortgage timetable must fit inside the arras deadline, not the other way round. A completion date thirty days away leaves no room for a non-resident file. Ask your lawyer for a financing condition that covers both a refusal and an offer reduced by a low valuation.
Application and documents: weeks 1 to 3
Lenders ask the same questions of every non-resident file: is the income real, will it last, and what is it worth in euros? A complete file is read in days. An incomplete one comes back with questions, and each round can cost a week.
Three things slow most foreign files:
- Translations. Payslips, tax returns and employment contracts may need translating. Ask which ones before you pay for them.
- Apostilles. Some foreign public documents need the Hague Apostille, issued in the country that produced them. Start early.
- Origin of funds. Anti-money-laundering rules require the lender and the notary to trace your deposit. Statements in your own name, with the source explained, prevent weeks of questions. Our guide to moving money to Spain covers the paper trail.
The non-resident mortgage checklist lists what to gather before you apply.
The valuation: why does it matter so much?
The lender has the property valued by an approved valuation company, whose valuer visits it. You pay for the valuation: Law 5/2019 assigns that cost to the borrower, while the notary, registry and agency costs of the mortgage fall on the lender. Under article 3 bis of Law 2/1981, the lender must also accept a valuation you provide, if it was certified by an approved valuer and has not expired.
The figure matters because Spanish lenders apply the loan percentage to the lower of the price and the valuation.
Worked example. A non-resident buys a €400,000 resale home with 70% financing:
| Valuation at the price | Valuation at €380,000 | |
|---|---|---|
| Loan (70%) | €280,000 | €266,000 |
| Deposit you fund | €120,000 | €134,000 |
| Extra cash needed | none | €14,000 |
Taxes and costs come on top in both columns. Order the valuation as soon as the price is agreed, so any shortfall appears while there is still time to react.
Approval, then the FEIN and the FiAE
After the valuation, the lender’s risk team approves or declines the loan. Approval is not yet the offer. Article 14 of Law 5/2019 sets out what you must receive at least ten calendar days before signing:
- the FEIN, the European Standardised Information Sheet: your personalised offer, binding on the lender for the agreed period, which must be at least ten days;
- the FiAE, the Standardised Warnings Sheet, which flags the key clauses: the reference index, any interest-rate floor, early termination for non-payment, the allocation of costs and whether the loan is in a foreign currency;
- for a variable-rate loan, a separate document showing the instalments under different interest-rate scenarios;
- a copy of the draft contract;
- clear information on costs and, if the lender requires insurance, on the policy;
- a notice that you are entitled to free, personalised advice from the notary you choose.
Article 3 makes the law mandatory, so the ten days cannot be waived to sign sooner. Use them to read the documents and ask questions.
The transparency meeting at the notary
During those ten days you visit the notary you have chosen. Article 15 requires you, or someone representing you for that purpose, to appear no later than the day before signing. The notary checks that the documents were delivered on time, explains the clauses, answers your questions and asks you to complete a test on the information received. It is all recorded in a notarial act, the acta de transparencia, which carries no notary fee.
If the documents were late or you do not appear, the notary records it and cannot authorise the mortgage deed. The advice is given in person, so if you will not be in Spain, the power of attorney must cover this meeting expressly. Our guide to buying with a power of attorney explains how to grant one from abroad.
Signing day: purchase and mortgage together
The purchase deed and the mortgage deed are normally signed one after the other, before the same notary, on the same day. The seller receives the price, partly from the loan the lender pays out and partly from your funds, and you receive the keys. Your contribution and the taxes must already be in Spain, so do not schedule the last transfer for the day before.
After signing: taxes and registration
Purchase taxes are paid within the deadline set by each region. Under article 254 of the Mortgage Act, the Land Registry will not register a deed until the taxes it triggers are paid. Once the deed is presented, article 18 gives the registrar a maximum of fifteen days from the presentation entry to register it. An agency or your lawyer usually handles both steps.
What can you do from abroad?
| Step | From abroad? | How |
|---|---|---|
| Feasibility review and documents | Yes | Email and video call |
| NIE | Yes | Spanish consulate, or a representative where the office accepts it |
| Spanish bank account | Depends on the bank | Ask before you plan the trip |
| Valuation | Yes | The valuer visits the property, not you |
| FEIN, FiAE and draft contract | Yes | Delivered to you; read them with your adviser |
| Transparency meeting | Only through a representative | In person, or by power of attorney |
| Purchase and mortgage deeds | Only through a representative | In person, or by power of attorney |
| Taxes and registration | Yes | Handled by an agency or your lawyer |
What usually makes it take longer?
- Documents without translation or apostille, discovered after the file has gone to the lender.
- Unexplained money: transfers through several accounts, or gifts without supporting documents.
- A valuation below the price, which reduces the loan and can reopen the approval.
- An arras deadline that is too short, which turns a normal delay into a risk to your deposit.
- Names that do not match across passport, NIE and bank documents.
- A power of attorney that arrives late, or does not cover both the mortgage and the notary meeting.
Checklist: before you sign the arras
- My feasibility review assumes 60–70% financing, not 80%.
- I have counted taxes and costs on top of a 30–40% contribution.
- My NIE is issued or in progress, and the Spanish account is arranged.
- My income, tax and bank documents are gathered and translated where needed.
- The origin of my funds is documented.
- The completion date allows six to ten weeks from a complete file, plus a margin.
- The financing condition covers a refusal and a low valuation.
- I know whether I will sign in person or by power of attorney.
How RCG coordinates it
RCG Finance is a real-estate credit intermediary registered with the Bank of Spain under number E760, with an office in Salou. We prepare the file once, present it to the lenders that finance non-residents and keep the valuation, the offer and the notary on one timetable, while our partner lawyer handles the legal side. We only charge if we get your mortgage. The lender makes the final decision, so we do not promise approval or dates.
What to do next
Size the cash with the purchase costs calculator. When the numbers work, our non-resident mortgage service puts the file in front of the right lenders.
Sources and review
Prepared by the RCG Finance editorial team (RCG 2026 S.L., Bank of Spain register of credit intermediaries no. E760) and reviewed by Rafael, founder of RCG Finance and former debt and M&A advisor at KPMG and PwC, under our editorial standards. Last source review: 1 October 2026.
- Spanish Official Gazette — Law 5/2019 on real-estate credit, articles 3, 14 and 15
- Bank of Spain — All the information about your future mortgage in one sheet (FEIN)
- Bank of Spain — What information will you receive from the notary when you sign your mortgage agreement?
- Bank of Spain — You can use a notary of your own choice
- Spanish Official Gazette — Law 2/1981 on the mortgage market, article 3 bis (valuation provided by the client)
- Spanish Official Gazette — Mortgage Act, articles 18 and 254
- Spanish Official Gazette — Civil Code, article 1454 (arras)
Frequently asked questions
How long does it take to get a mortgage in Spain?
For a non-resident, usually six to ten weeks from a complete file to signing at the notary. Add the weeks before that to obtain an NIE, open a Spanish account and gather translated documents. The last ten calendar days are a legal minimum under Law 5/2019 and cannot be shortened.
What are the steps to get a mortgage in Spain as a non-resident?
Feasibility review, NIE and Spanish account, reservation and arras contract, application with your documents, valuation, credit approval, the FEIN and FiAE at least ten calendar days before signing, the transparency meeting at the notary, signing the purchase and mortgage deeds, and registration.
Can I get a Spanish mortgage without travelling to Spain?
Yes. Almost every step can be handled from abroad. The transparency meeting and the signing need you in person or a representative with a power of attorney that expressly covers both. Grant it early, because apostilles, translations and couriers all take time.
Can the ten-day period before signing be waived?
No. Article 3 of Law 5/2019 makes its rules mandatory, so the parties cannot agree to shorten them. The lender must deliver the FEIN, the FiAE and the draft contract at least ten calendar days before signing, and you must see the notary no later than the day before.